Support rings and steel elevator-shaft structures as load-bearing frameworks for reinforced-concrete slabs
Together with the Döppersberg joint venture (ARGE), consisting of MBN Bau AG and Wittfeld GmbH, Rheiner Stahlbau GmbH is involved in the construction of a two-storey parking deck with bus terminal and shopping mall at Wuppertal’s main railway station. This project is part of the redesign of Wuppertal Central Station and is currently the most important urban-development undertaking for the coming years, as well as a flagship project for the entire region. The parking deck will provide around 240 new car parking spaces. The new shopping mall will offer space for approximately 20 larger and smaller retail units. The underground interior of the mall spans nearly 50 m; the slab is supported by so-called support rings and elevator-shaft structures. These steel structures meet high architectural standards while simultaneously contributing to the building’s structural stability through their supporting function.
Given the architectural requirements in combination with the extraordinary dimensions, fabricating the steel structures is a particular challenge for Rheiner Stahlbau GmbH, as it pushes the limits of production capacity in some areas. For the load-bearing ring beams, individual segments with material thicknesses of up to 150 mm are joined by full-penetration butt welds, because—at over 3.80 m in diameter—they are not available as single pieces. The obliquely oriented and irregularly arranged tubular columns are round hollow sections with wall thicknesses up to 45 mm, welded to the ring beams at the joints. Owing to these material thicknesses, the stringent requirements for weld quality are especially demanding; an independent procedure qualification for narrow-gap welding had to be applied for specifically for this work. The welding equipment required for this was purchased in previous financial years and formed the basis for fulfilling the task.
Fabrication can only be carried out with the components in a horizontal position because of their overall dimensions. As a result of the constrained welding positions this entails when joining the individual parts, RSB used preheating of the welds with induction-heating systems for the first time. All support rings and elevator-shaft structures are fully assembled at the plant and delivered to the construction site as oversize loads.