Steel structure in Übach-Palenberg Assembly of conveyor bridge structure As part of a construction project in Übach-Palenberg (North Rhine-Westphalia), we manufactured, delivered, and assembled the steel structure for a conveyor bridge. Due to the limited space available on the construction site, the conveyor bridge structure was pre-assembled at a pre-assembly site outside the construction site in five individual elements, each weighing approx. 30 t. On the agreed assembly date, the individual elements were transported from the pre-assembly site to the installation site via the factory road using self-propelled hydraulic lifters. The individual elements were assembled into the overall structure at the installation site. The total weight of the conveyor bridge was 150 tons. Two 500-ton mobile cranes were used to mount it on the pre-assembled support frames. The assembly of the individual elements at the installation site, including lifting, was completed within 24 hours over a weekend.