Capacity expansion of Kitchen III for apetito in Rheine

Leistungen: Dach- und Fassadenbau SFB Industrial Construction steel construction

Process Optimization for Community Catering
apetito provides solutions for both communal and individual catering in the form of deep-frozen products and systems, serving schools, companies, and healthcare facilities, among others. In close cooperation with MBN GmbH and the planning office rpg, we expanded the production capacities of apetito AG at the Rheine site on a turnkey basis, including the technical building equipment.

The construction project at the existing Kitchen III was carried out in two phases. In the first phase, completed by May 2018, the existing building to the south was extended with a two-storey annex housing a supply area and two production lines, each including processing, freezing, and packaging facilities. At the former workshop site, the new “Individually Quick Frozen Center” was added, where processing and distribution of goods takes place directly following production. The kitchen expansion also required the extension of refrigeration, sprinkler, and power supply systems, which were installed in a new two-storey technical center. To meet current emissions-control regulations, six exhaust stacks, each 6 meters high, and two ventilation systems for required smoke extraction were installed on the roof of the existing production hall. These prefabricated units were lifted onto the roof by helicopter.

In the second phase, the office and social facilities were extended on the northern side along Karmannstraße with a new two-storey building and an additional floor built onto the existing structure. The direct connection to the existing buildings ensured shorter staff routes and optimized workflows with the separation of “black/white” hygiene areas. The very high hygiene standards required in food processing, combined with the need to integrate construction into ongoing, uninterrupted production, were major challenges of this project.

Because of the many interfaces and dependencies between the different work areas, construction processes were continuously monitored and optimized in cooperation with the apetito project team. Thanks to our process optimization, we were able to complete the project three months ahead of schedule.